5 November 2020

We have been communicating with the Project Manager from Gio Construction who will be doing the fibre build.

He has informed me that they have dispatched a team to scout the area to identify the existing Telkom/Openserve infrastructure, which would form the basis of their new fibre design.

The fibre build will commence in early January/February 2021, with the expected Go Live before the end of March 2021.